Contract Value: =N=20,032,273.80;
Year: 2018;
Awardee: FHQ; Zone: ZONE 10; Command: Kebbi; State: Kebbi; LGA: JEGA; Site: JEGA, KOKO AND MAYAMA ; Contractor: Messrs. PLATINUM PROJECTS LIMITED;
Coordinator: SANNI;

Contract Value: =N=13,354,849.20;
Year: 2018;
Awardee: FHQ; Zone: ZONE 10; Command: Kebbi; State: Kebbi; LGA: KALGO; Site: ALIERO AND KALGO; Contractor: Messrs. Dogaro Global Services Ltd.;
Coordinator: SANNI;

Contract Value: =N=26,709,698.40;
Year: 2018;
Awardee: FHQ; Zone: ZONE 10; Command: Kebbi; State: Kebbi; LGA: LAGOS ISLAND; Site: Not Specified; Contractor: Messrs. Jak-Kana Integrated Concepts Ltd;
Coordinator: SANNI;

Contract Value: =N=13,973,431.50;
Year: 2005;
Awardee: FHQ; Zone: ZONE 10; Command: Kebbi; State: Kebbi; LGA: LAGOS ISLAND; Site: Not Specified; Contractor: Messrs. Siliki Investment;
Coordinator: Emoh;
Top