Monthly Progress Report (PRG): Report on the fencing project: LotNo F180005; 2018

i hereby write to notify that the substructurel works have been satisfactorily completed..

Milestones are
Excavations, foundation,fillings around foundation, concrete floor slab.
.
.
A well cured sandcrete blocks were used.

Recommendations: Contractor recommended for the next stage of payment.