Interim Certificate Report (ICR): Construction of 1No. 8 Man rank and File quarters: LotNo F048; 2007
The Contractor has done a 50% stage of Work, it is hereby recommended for payment, for the job done
The Contractor has done a 50% stage of Work, it is hereby recommended for payment, for the job done
AFTER THE CLEARING OF THE SITE AND THE BLOCKWORK HAS BEEN COMPLETED , THE COMMUNIITY INVADED THE SIT
The Construction of 3No. Borehole has Completed 100%
THE JOB IS AT BLOCKWORK COMPLETION STAGE AND IS RECOMMENDED FOR 30% PAYMENT PLEASE.
The contractor moved to site on the 15th December, 2019, he has so far carried out a 50% stage of jo
I WRITE TO BRING TO THE AUTORITY THAT FOR OVER THREE WEEKS NOW , WE HAVE NOT BEEN ABLE TO ACCESS MY
I WRITE TO NOTIFY THE AUTORITY THAT THE CONTRACTOR HAS COMMENCE THE WORK AND FINISH ALL THE BLOCKWOR